Get connected to the largest online education portal to get help with OPS 571 Week 4 Quiz if you need extra support with your course material, Tutorial Services can help. Whether you want any help regarding assignment answers & question. Uop E Assignments is one of the best online tutorial store. We provide quality guidance to the students of University of Phoenix at affordable price.

OPS 571 Week 4 Quiz

$8.99 - $ 11.99

Rating: A+

Purchased: 29 Times

Description



OPS 571 Week 4 Quiz -

1. A work breakdown structure is

  • a hierarchy of tasks, subtasks, and work packages
  • a Cost and Performance tracking schedule
  • a structure that is incompatible with the Critical Path Method
  • a simple list of the activities making up a project

2. The vertical axis on a Gantt chart is usually which of the following?

  • Activities
  • Time
  • Cost
  • Profit

3. Which of the following identifies a key principle of Reengineering?

  • Organize around tasks.
  • Downsize (layoff) workers and do the same amount of work as before.
  • Merge information processing work into the real work that produces the information.
  • Capture information both at the source and where it is interpreted.

4. At the onset, a project originates as which of the following?

  • A Gantt chart
  • A series of milestones
  • Critical path method (CPM)
  • A statement of work (SOW

5. Consulting firms typically use which of the following techniques to plan and monitor the engagements of the firm or specific projects?

  • CPM/PERT
  • Qualitative forecasting
  • Materials requirements planning (MRP)
  • Quantitative layout

6. A Responsibility Chart specifically identifies which of the following?

  • Planning the tasks for a project
  • Customer satisfaction
  • Commitment to quality
  • Level of inventory

7. Which of the following would be the result of subdividing a project?

  • Job orders
  • Work events
  • Job categories
  • Tasks

8. Which project progress technique includes the essential features of a project plan, budgeted cost of work scheduled and budgeted cost of work performed?

  • Earned value management
  • Critical path method
  • Cost analysis
  • Gantt chart

9. An example of a graphic project report utilized within project management is:

  • Project proposal
  • Equipment and supplies chart
  • Humphrey chart
  • Cost and performance tracking schedule